Vallecito Dam Construction Project
Pages
-
-
Forms in place for left wall footing
-
Forms in place for left wall footing between stations 8+30 and 8+65. Top of form is on finished floor grade. Rough-grading has been completed by general contractor, and has been turned over to sub-contractor for fine-grading, Average depth of over-excavation is 4 inches in this area., Original photo number: Pine R - 426
-
-
Foundation drainage system
-
Foundation drainage system. Note grout risers at right side of trench for grouting system after embankment has been placed., Original photo number: Pine R - 307
-
-
Gate chamber taking shape
-
Inside forms and reinforcement in place for outlet works gate chamber and spiral stairway addition, Original photo number: Pine R - 241
-
-
Gate structure
-
Looking downstream at completed gate structure., Original photo number: Pine R - 335
-
-
General view of contractor's camp
-
General view of camp constructed by the Martin Wunderlich Co. The three large buildings at the left are the commissary, mess hall and office., Original photo number: Pine R - 049
-
-
Grouting operations in outlet works
-
Grouting operations in outlet works near station 8+25. Grout mixer and pump are in the center of the picture., Original photo number: Pine R - 168
-
-
Hand-tamping around outlet conduit
-
View of hand-tamping operations around outlet conduit, taken fro the top of the left bank opposite outlet works station 8+85. Note embankment cut-off wall in left background., Original photo number: Pine R - 311
-
-
Inlet channel to outlet conduit
-
Inlet channel to outlet conduit, looking downstream. Structure seen in center is the concrete mixing plant., Original photo number: Pine R - 272
Pages